1. What percentage of plinth area of the residential building comes to carpet area?
    (A) 40 to 55%
    (B) 50 to 65%
    (C) 60 to 75%
    (D) 70 to 85% 

2. Which brick wall thickness is measured in sq.m?
    (A) 10 cm
    (B) 15 cm
    (C) 20 cm
    (D) 30 cm

3. What percentage of estimate cost is charged for centage charges?
    (A) 5 to 10%
    (B) 10 to 15%
    (C) 15 to 20%
    (D) 20 to 25%

4. What is the unit for cement concrete in M.K.S. system?
    (A) Nos.
    (B) m
    (C) sq.m
    (D) cu.m

5. Which data is necessary for the preparation of estimate?
    (A) Labor
    (B) Material
    (C) Fund
    (D) Drawings

6. What is the minimum cubical quantity for bill quantity calculation?
    (A) 1 mm3
    (B) 1 cm3
    (C) 0.01 m3
    (D) 0.1 m3

7. What is the measuring unit for soling layer?
    (A) m
    (B) sq.m
    (C) cu.m
    (D) Nos. 

8. How aggregate is specified?
    (A) Size in mm
    (B) Length in mm
    (C) Height and breadth in cm
    (D) Length in m, section in mm 

9. What percentage of estimate cost is charged for centage charges?
    (A) 5 to 10%
    (B) 10 to 15%
    (C) 15 to 20%
    (D) 20 to 25% 

10. What is the plastering area for a pillar?
    (A) Length × breadth × height
    (B) Section area × height
    (C) Perimeter
    (D) Perimeter × height

11. Which is an item rate estimate?
    (A) Plinth area
    (B) Annual repair
    (C) Cubical content
    (D) Preliminary

12. What is the unit for flooring in MKS system?
    (A) m
    (B) sq.m
    (C) cu.m
    (D) Nos.

13. What is the minimum lead for earth work excavation?
    (A) 10 m
    (B) 20 m
    (C) 30 m
    (D) 50 m