1. What is the minimum lead for earth work excavation?
    (A) 10 m
    (B) 20 m
    (C) 30 m
    (D) 50 m

2. What is the unit for brick work in cement mortar for superstructure in MKS system?
    (A) m
    (B) sq.m
    (C) cu.m
    (D) Nos.

3. How much area of the opening is ignored for the masonry quantity calculation?
    (A) 1 sq.cm
    (B) 10 sq.cm
    (C) 100 sq.cm
    (D) 1000 sq.cm

4. What is the plastering area for a pillar?
    (A) Length × breadth × height
    (B) Section area × height
    (C) Perimeter
    (D) Perimeter × height 

5. What is the name given to area of a building consisting of verandahʹs, passages, corridors, balconies etc.?
    (A) Circulation area
    (B) Horizontal circulation area
    (C) Vertical circulation area
    (D) Carpet area 

6. What is the density of mild steel?
    (A) 0.785 q/cu.m
    (B) 7.85 q/cu.m
    (C) 78.5 q/cu.m
    (D) 785 q/cu.m

7. What is the name given to area of a building consisting of verandahs, passages, corridors, balconies etc.?
    (A) Circulation area
    (B) Horizontal circulation area
    (C) Vertical circulation area
    (D) Carpet area

8. What is the sequence of booking measurements?
    (A) Breadth, length and depth
    (B) Number, length and depth
    (C) Diameter, length and density
    (D) Length, breadth and height 

9. What is the minimum cubical quantity for bill quantity calculation?
    (A) 1 mm3
    (B) 1 cm3
    (C) 0.01 m3
    (D) 0.1 m3

10. What is the unit for cement concrete in M.K.S. system?
    (A) Nos.
    (B) m
    (C) sq.m
    (D) cu.m 

11. How much area of the opening is ignored for the masonry quantity calculation?
    (A) 1 sq.cm
    (B) 10 sq.cm
    (C) 100 sq.cm
    (D) 1000 sq.cm

12. Which estimate is required for administrative sanction?
    (A) Approximate
    (B) Detailed
    (C) Revised
    (D) Supplementary 

13. Which estimate is prepared while the original sanctioned estimate is exceeded by more than 5%?
    (A) Supplementary
    (B) Extension and improvement
    (C) Revised
    (D) Plinth area

14. Which estimate is prepared while the expenditure on a work exceeds by more than 10%?
    (A) Supplementary
    (B) Revised
    (C) Annual repair
    (D) Cubical content