Estimating and Costing in Civil Engineering Objective - Set 03 - ObjectiveBooks

Estimating and Costing in Civil Engineering Objective - Set 03

Practice Test: Question Set - 03


1. For the construction of buildings, the subheads of the estimate are
    (A) Earthwork, Concrete work, Brick work
    (B) Brickwork, Stone work, Roofing
    (C) Brickwork Flooring, Wood work, Steel work
    (D) All the above

2. Pick up the correct statement from the following:
    (A) Pointing is measured in sq.m
    (B) Plastering is measured in sq.m
    (C) Glazing is measured in sq.m
    (D) All the above

3. The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is
Estimating and Costing-Set 03, Question No. 03
    (A) ⅓ × (b - rd)²/(r - s)
    (B) ⅓ × (b - rd)²/(r + s)
    (C) ½ × (b + rd)²/(r - s)
    (D) ⅓ × (b - rd)²/(s - r)

4. Pick up the correct statement from the following:
    (A) If the bed level is above N.S.L. the canal is called fully in baking and the berms are designed as 3 d where d is full supply depth of water (F.S.D.)
    (B) Area of canal in cutting = BD + Sd2 where B = bed width, d = depth of cutting and S is the side slope
    (C) If F.S.L. is above N.S.L the canal is called partly in cutting and partly in filling and berms are designed as 2d where d is full supply depth
    (D) All the above

5. Pick up the incorrect statement from the following:
    (A) No deduction is made for the volume occupied by reinforcement
    (B) No deduction is made for the openings upto 0.1 sq.m
    (C) No deduction is made for volumes occupied by pipes, not exceeding 100 sq.cm in cross-section
    (D) None of these

6. The value of 'B' of Indian type W.C. shown in the given figure is:


Estimating and Costing-Set 03, Question No. 06
    (A) 45 cm
    (B) 50 cm
    (C) 30 cm
    (D) 25 cm

7. Pick up the excavation where measurements are made in square meters for payment.
    (A) Ordinary cuttings up to 1 m
    (B) Surface dressing up to 15 cm depths
    (C) Surface excavation up to 30 cm depths
    (D) Both (b) and (c)

8. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken
    (A) 1.80 liters for 5 to 10 users
    (B) 1.20 liters for 15 users
    (C) 1.35 for 20 users
    (D) All the above

9. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and
    (A) Breadth of the wall
    (B) Half breadth of wall on each side
    (C) One fourth breadth of wall on each side
    (D) None of these

10. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
    (A) 1.5 m3
    (B) 2.5 m3
    (C) 3.5 m3
    (D) 5.0 m3

Show and hide multiple DIV using JavaScript View All Answers


 Next Tests: