1. The item of the brick structure measured in sq.m, is
    (A) Reinforced brick work
    (B) Broken glass coping
    (C) Brick edging
    (D) Brick work in arches

2. The most reliable estimate is
    (A) Detailed estimate
    (B) Preliminary estimate
    (C) Plinth area estimate
    (D) Cube rate estimate

3. The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is


Estimating and Costing-Set 05, Question No. 03
    (A) (6 + 15) chains
    (B) (6 + 12) chains
    (C) (6 + 18) chains
    (D) None of these

4. According to ISI method of measurement, the order of the sequence is
    (A) Length, breadth, height
    (B) Breadth, length, height
    (C) Height, length, breadth
    (D) None of these

5. Anti-siphonage pipe is connected to
    (A) Main soil pipe
    (B) Bottom of P trap W.C.
    (C) Top of P trap W.C.
    (D) Side of water closet

6. Pick up the correct statement from the following:
    (A) In a gully trap, a water seal of 6 to 7.5 cm is provided
    (B) The gully trap collects waste water from the kitchen, sink, wash basins, etc.
    (C) The gully trap disconnects the sullage drain from the main drainage system
    (D) The grating provided over gully traps is 23 cm square

7. Pick up the correct statement from the following:
    (A) Bricks are paid per thousand
    (B) Cement is paid per 50 kg bag
    (C) Lime is paid per quintal
    (D) All the above

8. Pick up the correct statement from the following:
    (A) All pipes and fittings are classified according to their diameters
    (B) The diameter of the pipes is the nominal diameter of internal bore
    (C) All pipes are measured along the centre line of the pipes in meters
    (D) All the above

9. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.
    (A) 26,000 m3
    (B) 26,500 m3
    (C) 27,000 m3
    (D) 27,500 m3

10. Pick up the correct statement in case of water supply.
    (A) Pipes laid in trenches and pipes fixed to walls are measured separately
    (B) Cutting through walls and floors are included with the item
    (C) Pipes are classified according to their sizes and quality
    (D) All the above