1. The damp proof course (D.P.C.) is measured in
    (A) Cub. m
    (B) Sq. m
    (C) Meters
    (D) None of these

2. The volume is measured correct to the nearest
    (A) 0.01 cum
    (B) 0.02 cum
    (C) 0.03 cum
    (D) 0.04 cum

3. If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm2 and bond stress is 6 kg/cm2, the required bond length of the rod is
    (A) 30 D
    (B) 39 D
    (C) 50 D
    (D) 59 D

4. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
    (A) 0.90 m3
    (B) 0.94 m3
    (C) 0.98 m3
    (D) 1.00 m3

5. Size, capacity and materials need be specified for
    (A) Bib-cocks
    (B) Stop-cocks
    (C) Ball valves
    (D) All the above

6. The expected out turn of half brick partition wall per mason per day is
    (A) 1.5 m3
    (B) 2.0 m3
    (C) 4.0 m2
    (D) 5.0 m2

7. The floor area includes the area of the balcony up to
    (A) 100 %
    (B) 75 %
    (C) 50 %
    (D) 25 %

8. The slope of the outlet of 'P trap' below the horizontal is kept
    (A) 8°
    (B) 10°
    (C) 12°
    (D) 14°

9. The weight of an item is measured correct to nearest
    (A) 0.25 kg
    (B) 0.50 kg
    (C) 0.75 kg
    (D) 1.00 kg

10. Berms are provided in canals if these are
    (A) Fully in excavation
    (B) Partly in excavation and partly in embankment
    (C) Fully in embankment
    (D) All the above