Practice Test: Question Set - 21
1. The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as
- (A) Duration
- (B) Total float
- (C) Free float
- (D) Interfering float
2. Work study is done with the help of
- (A) Process chart
- (B) Material handling
- (C) Stop watch
- (D) All of the above
3. Which of the following are the principles of material handling?
- (A) Keep
all the handling to the minimum
- (B) Select
only efficient handling equipment
- (C) Move
the heaviest weight to the least distance
- (D) All
of the above
4. Slack represents the difference between the
- (A) Latest allowable time
and the normal expected time
- (B) Latest allowable time
and the earliest expected time
- (C) Proposed allowable
time and the earliest expected time
- (D) Normal allowable time
and the latest expected time
5. Product layout is also known as
- (A) Analytical
layout
- (B) Synthetic
layout
- (C) Static
product layout
- (D) None
of these
6. A low unit cost can be obtained by following
- (A) Product layout
- (B) Functional layout
- (C) Automatic material
handling equipment
- (D) Specialization of
operation
7. The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as
- (A) Job
enlargement
- (B) Job
enrichment
- (C) Job
rotation
- (D) Job
evaluation
8. In order that linear programming techniques provide valid results
- (A) Relations between factors must be linear
(positive)
- (B) Relations between factors must be linear
(negative)
- (C) Either (A) or (B)
- (D) Only one factor
should change at a time, others remaining constant
9. Abbreviated work factor data is applied for
- (A) Material
handling operation
- (B) Maintenance
operation
- (C) Packing
and shipping operation
- (D) All
of these
10. An optimum project schedule implies
- (A) Optimum utilization
of men, machines and materials
- (B) Lowest possible cost
and shortest possible time for project
- (C) Timely execution of
project
- (D) To produce best
results under given constraints
11. Gantt chart gives information about
- (A) Scheduling
and routing
- (B) Sales
- (C) Production
schedule
- (D) Machine utilization
12. The main advantage of line organisation is its
- (A) Effective command and
control
- (B) Defined
responsibilities at all levels
- (C) Rigid discipline in
the organisation
- (D) All of the above
13. Which of the following type of layout is suitable for automobile manufacturing concern?
- (A) Product
layout
- (B) Process
layout
- (C) Fixed
position layout
- (D) Combination
layout
14. Pick up the correct statement from the following
- (A) Critical path method
is an improvement upon bar chart method
- (B) Critical path method
provides a realistic approach to the daily problems
- (C) Critical path method
avoids delays which are very common in bar chart
- (D) All of the above
15. The most important function of inventory control is
- (A) Stock
control system
- (B) To
run the stores effectively
- (C) Technical
responsibility for the state of materials
- (D) All
of the above