Multiple Choice Questions on Industrial Engineering - Set 14 - ObjectiveBooks

Multiple Choice Questions on Industrial Engineering - Set 14

Practice Test: Question Set - 14


1. Process layout is employed for
    (A) Batch production
    (B) Continuous type of product
    (C) Effective utilization of machines
    (D) All of the above

2. Under the Apprenticeship Act
    (A) All industries have to necessarily train the apprentices
    (B) Industries have to train apprentices according to their requirement
    (C) All industries employing more than 100 workers have to recruit apprentices
    (D) Only industries employing more than 500 workers have to recruit apprentices

3. Direct expenses include
    (A) Factory expenses
    (B) Selling expenses
    (C) Administrative expenses
    (D) None of these

4. In the Halsey 50-50 plan, the following are rewarded more
    (A) Past good workers
    (B) Past poor workers
    (C) Past average workers
    (D) All of the above

5. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker
    (A) Whose output exceeds 67% efficiency
    (B) On the percentage of time saved
    (C) On the percentage of time worked
    (D) On the percentage of standard time

6. PERT is the
    (A) Time oriented technique
    (B) Event oriented technique
    (C) Activity oriented technique
    (D) Target oriented technique

7. In product layout
    (A) Specialized and strict supervision is required
    (B) Machines can not be used to their maximum capacity
    (C) Manufacturing cost rises with a fall in the volume of production
    (D) All of the above

8. Emergency rush order can be pushed more effectively in
    (A) Job production
    (B) Automatic production
    (C) Continuous production
    (D) Intermittent production

9. Earliest finish time can be regarded as
    (A) Earliest start time + duration of activity
    (B) Earliest start time duration of activity
    (C) Latest finish time + duration of activity
    (D) Latest finish time duration of activity

10. The assumption in PERT is
    (A) A project will always be behind schedule, if left uncorrected
    (B) Cost of project will always be more than the estimated cost, if no timely corrections are taken
    (C) A project can be subdivided into a set of predictable, independent activities
    (D) Activities are fixed and can't be changed

11. Which of the following wage incentive plan is applied to all workers?
    (A) Halsey plan
    (B) Gantt plan
    (C) Emerson's efficiency plan
    (D) Rowan plan

12. According to MAPI formula, the old machine should be replaced by new one when
      (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum)
    (A) CAM < DAM
    (B) CAM > DAM
    (C) CAM = DAM
    (D) There is no such criterion

13. TMU in method time measurement stands for
    (A) Time motion unit
    (B) Time measurement unit
    (C) Time movement unit
    (D) Technique measurement unit

14. Gantt chart is used for
    (A) Inventory control
    (B) Material handling
    (C) Production schedule
    (D) Machine repair schedules

15. The term 'value' in value engineering refers to
    (A) Total cost of the product
    (B) Selling price of the product
    (C) Utility of the product
    (D) Manufactured cost of the product

Show and hide multiple DIV using JavaScript View All Answers


 Next Tests: