Industrial Engineering MCQ - Set 02 - ObjectiveBooks

Industrial Engineering MCQ - Set 02

Practice Test: Question Set - 02


1. CPM is the
    (A) Time oriented technique
    (B) Event oriented technique
    (C) Activity oriented technique
    (D) Target oriented technique

2. PERT
    (A) Provides an approach for keeping planning up-to-date
    (B) Provides a way for management to require that planning be done on a uniform and logical basis
    (C) Permits management to foresee quickly the impact of variations from the plan
    (D) All of the above

3. The probability distribution of activity times in PERT follows following distribution
    (A) Normal
    (B) Binomial
    (C) Beta
    (D) Exponential

4. Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
    (A) Consumes time, but no resources
    (B) Consumes resources but no time
    (C) Consumes neither time nor resources
    (D) Is a dangling event

5. In the cost structure of a product, the selling price is determined by the factors such as
    (A) Sales turn over
    (B) Lowest competitive price
    (C) Various elements of the cost
    (D) All of the above

6. Work study is concerned with
    (A) Improving present method and finding standard time
    (B) Motivation of workers
    (C) Improving production capability
    (D) Improving production planning and control

7. Which of the following are the guidelines for the construction of a network diagram?
    (A) Each activity is represented by one and only one arrow in the network
    (B) Dangling must be avoided in a network diagram
    (C) Dummy activity consumes no time or resource
    (D) All of the above

8. ABC analysis deals with
    (A) Analysis of process chart
    (B) Flow of material
    (C) Ordering schedule of job
    (D) Controlling inventory costs money

9. Breakeven analysis is a
    (A) Short term analysis
    (B) Long term analysis
    (C) Average of short and long term analysis
    (D) Any one of these

10. The appellate authority for an industrial dispute is
    (A) Management
    (B) Labour court
    (C) High court/supreme court
    (D) Board of directors

11. Which of the following layouts is suited to job production?
    (A) Process layout
    (B) Product layout
    (C) Fixed position layout
    (D) Plant layout

12. 'Value' for value engineering and analysis purposes is defined as
    (A) Purchase value
    (B) Saleable value
    (C) Depreciated value
    (D) Function/cost

13. Replacement studies are made on the following basis
    (A) Annual cost method
    (B) Rate of return method
    (C) Total life average method
    (D) Any one of the above

14. The product layout
    (A) Lowers overall manufacturing time
    (B) Requires less space for placing machines
    (C) Utilizes machine and labour better
    (D) All of these

15. The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode
    (A) Early finish
    (B) Early start
    (C) Late start
    (D) Late finish