Practice Test: Question Set - 09
1. In the Halsey system of wage incentive plan, a worker is
- (A) Paid as per
efficiency
- (B) Ensured of minimum
wages
- (C) Not paid any bonus
till his efficiency
- (D) Never a loser
2. In order to avoid excessive multiplication of facilities, the layout preferred is
- (A) Product
layout
- (B) Process
layout
- (C) Group
layout
- (D) Static
layout
3. The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as
- (A) Dry work Plan
- (B) Halsey Premium Plan
- (C) Taylor Plan
- (D) Rowan Plan
4. The purpose of micro-motion study is to
- (A) Assist in
finding out the most efficient way of doing work
- (B) Train
the individual operator regarding the motion economy principles
- (C) Help
in collecting the motion time data for synthetic time standards
- (D) All of the
above
5. Monte Carlo solutions in queuing theory are extremely useful in queuing problems
- (A) That can't be analysed mathematically
- (B) Involving multistage
queuing
- (C) To verify mathematical results
- (D) All of the above
6. For material transportation, conveyors are used when the prevailing conditions include
- (A) Loads
are uniform
- (B) Routes
do not vary
- (C) Materials
move relatively continuously
- (D) All
of these
7. The difference between the time available to do the job and the time required to do the job, is known as
- (A) Event
- (B) Float
- (C) Duration
- (D) Constraint
8. Which of the following statement is correct?
- (A) When
slack of an activity is zero, it falls only on critical path.
- (B) CPM
technique is useful to minimize the direct and indirect expenses.
- (C) Critical
path of a net work represents the minimum time required for completion of
project.
- (D) All of the
above
9. The time which results in the least possible direct cost of an activity is known as
- (A) Normal time
- (B) Slow time
- (C) Crash time
- (D) Standard time
10. Which of the following statement is correct about the network diagram?
- (A) The
events are represented graphically by circles or nodes at the beginning and the
end of activity by arrows.
- (B) The tail end
of the arrow represents the start of an activity.
- (C) The head of
the arrow represents the end of an activity.
- (D) All of the
above
11. In PERT analysis, critical path is obtained by joining events having
- (A) +ve slack
- (B) -ve slack
- (C) Zero slack
- (D) Dummy activities
12. According to Rowan plan of wage incentive system, bonus is paid to a worker
- (A) Whose
output exceeds 67% efficiency
- (B) On
the percentage of time saved
- (C) On
the percentage of time worked
- (D) On the percentage
of standard time
13. Templates are used for
- (A) A planning layout
- (B) Flow of material
- (C) Advancing a programme
in automatic machines
- (D) Copying complicated
profiles
14. Line organization is suitable for
- (A) Sugar
industries
- (B) Oil
refining industries
- (C) Spinning
and weaving industries
- (D) All of these
15. What does symbol 'V' employ in work study
- (A) Operation
- (B) Inspection
- (C) Delay/ temporary Storage
- (D) Permanent storage
Next Tests: