Industrial Engineering online Practice Test - Set 08 - ObjectiveBooks

Industrial Engineering online Practice Test - Set 08

Practice Test: Question Set - 08


1. The average time recorded by work study man for an operation is called
    (A) Standard time
    (B) Normal time
    (C) Representative time
    (D) None of these

2. Which one of the following represents a group incentive plan?
    (A) Halsey Premium Plan
    (B) Lincoln Plan
    (C) Rowan Plan
    (D) Taylor Plan

3. Indirect expenses include
    (A) Factory expenses
    (B) Selling expenses
    (C) Administrative expenses
    (D) All of these

4. Which of the following equations is not in conformity with others?
    (A) Organization performance × motivation = profits
    (B) Knowledge × skill = ability
    (C) Ability × motivation = performance
    (D) Attitude × situation = motivation

5. Time study is carried out to determine the time required to complete job by
    (A) A slow worker
    (B) A fast worker
    (C) An average worker
    (D) An apprentice

6. Pick up the correct step used for scheduling a project by C.P.M.
    (A) A project is divided into various activities
    (B) Required time for each activity is established
    (C) Sequence of various activities is made according to their importance
    (D) All of the above

7. Linear programming can be applied successfully to
    (A) Chemical industry
    (B) Oil industry
    (C) Banks
    (D) All of these

8. The technique for establishing and maintaining priorities among the various jobs of any project is known as
    (A) Event flow scheduling technique
    (B) Critical ratio scheduling
    (C) Slotting technique for scheduling
    (D) Short interval scheduling

9. The value engineering technique in which experts of the same rank assemble for product development is called
    (A) Delphi
    (B) Brain storming
    (C) Morphological analysis
    (D) Direct expert comparison

10. Activity slack or float of any event on a PERT/CPM chart is represented by
    (A) Latest start time of succeeding event earliest finish time of preceding event activity time
    (B) Latest start time of the event earliest start time of the event
    (C) Latest finish time of event earliest finish time of the event
    (D) Anyone of the above

11. In time study, the rating factor is applied to determine
    (A) Standard time of a job
    (B) Merit rating of the worker
    (C) Fixation of incentive rate
    (D) Normal time of a worker

12. Which of the following organizations is best suited for steel plants
    (A) Functional organization
    (B) Line organization
    (C) Staff organization
    (D) Line, staff and functional organizations

13. What does symbol 'D' imply in work study?
    (A) Inspection
    (B) Transport
    (C) Delay/temporary storage
    (D) Permanent storage

14. The grouping of activities into organizational units is called
    (A) Corporate plans
    (B) Higher level management
    (C) Functional authority
    (D) Departmentation

15. Pick up the incorrect statement about advantages of work sampling
    (A) Permits a fine breakdown of activities and delays
    (B) Simultaneous study of many operators may be made by a single observer
    (C) Calculations are easier, method is economical and less time consuming
    (D) No time measuring devices are generally needed

Show and hide multiple DIV using JavaScript View All Answers